I. Maximum Testing Capacity of This Project
34.5/0.4 kV, dry-type transformers with capacity up to 15,000 kVA and impedance ranging from 4% to 14%;
6/0.4 kV, dry-type transformers with capacity up to 10,000 kVA and impedance ranging from 4% to 14%;
Maximum loss: 180 kW
II. Test Items
(1) Measurement of no-load loss and no-load current of transformers
(2) Calculation of no-load current percentage of transformers
(3) Measurement of load loss of transformers and conversion to standard temperature (at 100% current)
(4) Measurement of short-circuit impedance of transformers and conversion to standard temperature
(5) Induced voltage withstand test for transformers
(6) Power-frequency withstand test for transformers
(7) Partial discharge test for transformers
III. Project Highlights
Semi-automatic staged wiring, flexible operation, compatible with customers’ existing production processes
Integration of high-precision measuring instruments, stable and reliable data, compliant with international and Indonesian local standards
Support for customized test reports, compatible with customers’ production management systems
Mature solutions with rapid delivery, including on-site commissioning and training as a one-stop service
IV. Commissioning Information
Customer: PT. Trafoindo Prima Perkasa (Jakarta, Indonesia)
Commissioning date: January 2026
Operating status: Installation and commissioning completed, stably serving batch production testing